Acitvities
-
Overall concept, evaluation and realisation
-
Installation of 5 groundwater wells in 35 m depth
-
Reducing the temperature of the building by under floor cooling
-
Cleaning of the groundwater prior to filtration using an activated carbon filter
-
Bivalent heating system, thermal probes in combination with conventional heating system
Technical data
-
Heat capacity of 2.5 MW
-
Cooling capacity: 1.5 MW
Period
-
1995 - 1999
Location
-
Düsseldorf, Germany